We were appointed by Gower Landscape Partnership Scheme in January 2017 to work with the Community of Penclawdd over the next few months to facilitate decisions as to their selected heritage projects as part of the Gower LPS and also identify other projects that could be developed in the future.

Working with a range of people from the community, through workshops, discussion and a drop-in session R4C helped the informal working group establish agreed projects for development and prioritise them, so that they are able to have real activity within the community in the current year, as well as planning for future. A final report was delivered in early March to allow the community to obtain the necessary funding and agreements to commence activity in spring 2017